Company History
1999
- Barak Valley Cements Limited was incorporated on 28th April.
- The company received the certificate for commencement of business in April.
2001
- The company commenced commercial production on 1st April with an installed capacity of 300 TPD.
- The company received the Grant of ISI Mark (BIS Licence) for OPC 43 Grade in May.
2002
- The company's total turnover was Rs. 1829.77 Lacs for FY 2001-02.
2003
- The company received the ISI Mark (BIS Licence) for PPC in September.
- The company received ISO 9001: 2000 certification in September.
2005
- The company's total turnover was Rs. 5352.71 lacs for FY 2005-06.
2006
- The company achieved its best production of cement at 15750 MT in March.
2007
- The subsidiary started production in April.
2008
- The 6 MW Biomass based thermal Power Plant project was completed and ready to start commercial production.
2011
- Ms. Nidhi Sharma was appointed as Company Secretary and Compliance Officer.
2013
- Ms. Bhavna Jangid was appointed as Company Secretary and Compliance Officer.
2014
- Mr. Kamakhya Chamaria was appointed as Managing Director of the company.
2017
- The company commenced commercial production from the expanded capacity.
- The total production capacity of the Cement Grinding Unit increased to 1000 TPD.